Microsoft Project 2010 Manually Selected Milestones are getting automatically updated RRS feed

  • Question

  • My Manually Scheduled milestones get updated when I link a task to it.   For example: the milestone is 7/31/14, when I link a task to it with a completion date of 6/15/14, the milestone changes to 6/15/14.
    Friday, May 31, 2013 5:41 PM

All replies

  • tlengels --
     
    I already answered your question once.  Did you not see the answer or did you not like the answer?  Let us know.

    Dale A. Howard [MVP]

    Friday, May 31, 2013 8:37 PM
    Moderator