I want to complete a task using 50% of resource 1 and 50% of resource 2. HELP, PLEASE. RRS feed

  • Question

  • I have task #1 with 2.5 days of duration. 

    How can I complete this using 50% of the workday of resource 1 and 50% of the workday of resource 2 without extending the duration? I have a time restriction. 

    What configuration changes do I need to make? Do I need to change the task type or something else?

    Help, please.

    Thanks in advanced.


    • Edited by efebo Saturday, October 10, 2015 3:01 PM
    Saturday, October 10, 2015 11:29 AM

All replies

    1. Show the Gantt Chart view (or any task view).
    2. On the View ribbon, click the Details checkbox in the Split group to display the Task Form in the lower portion of the screen.
    3. Select the first resource underneath Resource Name.
    4. Enter 50 in the units field.
    5. Select the second resource underneath the first.
    6. Enter 50 in the units field.
    7. Click OK to create the assignments.

    Each resource will have 10 hours of work in the 2.5 day duration task.

    Saturday, October 10, 2015 12:20 PM