updating progress RRS feed

  • Question

  • Hello

     While updating project, project assigning constraint on many tasks, what could be the possible reason? I am doing rescheduling task after today's date. Getting below notification and task going into starting no earlier than today's date.

    so everytime i rebaseline, project will put this constraint?

     
    • Edited by Nimo007 Monday, April 11, 2016 10:51 AM
    Monday, April 11, 2016 10:50 AM

Answers

  • Hello,

    Baselines do not contain constraints.

    When you rebaseline, the new start/finish dates will be copied into baseline start/beseline finish.

    When ÿou ask Project to reschedule tasks after today, the way the scheduling engine does that is by putting a SNRT constraint on the task - there is no other way.

    Greetings,

    • Marked as answer by Nimo007 Monday, April 11, 2016 1:14 PM
    Monday, April 11, 2016 11:51 AM
    Moderator

All replies

  • Hello,

    Baselines do not contain constraints.

    When you rebaseline, the new start/finish dates will be copied into baseline start/beseline finish.

    When ÿou ask Project to reschedule tasks after today, the way the scheduling engine does that is by putting a SNRT constraint on the task - there is no other way.

    Greetings,

    • Marked as answer by Nimo007 Monday, April 11, 2016 1:14 PM
    Monday, April 11, 2016 11:51 AM
    Moderator
  • Ok Thanks