MS Project 2016 – Assignment Work not Rolling up to Resource RRS feed

  • Question

  • Does anyone have an idea why this is happening?

    Situation: 

    1. In MSP 2016 (64-bit), the work of new assignments does NOT roll up to the Resource.Work field.
    2. If the same project contains Assignment Work that was created using an earlier Project version (e.g. 2010 32-bit), then those assignments correctly roll up.
    3. When the same project is opened in MSP 2010 (32-bit), all Assignment Work correctly rolls up.

    There seems to be a new, deeply-hidden assignment attribute applied in MSP 2016, but I haven't been able to find it. 

    Monday, August 19, 2019 9:06 PM

All replies

  • Hi, I cannot replicate this on the latest version of the Project Online Desktop Client (32 bit).  I suggest you open a support call with Microsoft.

    Ben Howard [MVP] | web | blog | book | downloads | P2O


    Monday, August 19, 2019 9:17 PM
    Moderator
  • Thanks Ben,

    I'm hoping someone with a 64-bit local CTR installation (on 64-bit Windows 10 Pro for Workstations) can chime in before taking the next step....  So far, this has not been a problem worth spending money on.  It's just annoying.  BTW, local and internet-based repairs of the install had no effect.

    Tuesday, August 20, 2019 12:48 PM