    The formula for % Complete is:

    % Complete = (Actual Duration / Duration) x 100

    As you can see in the preceding formula, % Complete is actually % Duration Complete.  The formula for % Work Complete is:

    % Work Complete = (Actual Work / Work) x 100

    Hope this helps.