Negative Fixed Cost in Baseline Not reflected in Reporting database RRS feed

  • Question

  • We have Project Server 2010 SR1 with June 2012 CU and Project Client with December 2011 CU.

    Consider the following:

    • A summary task has three subtasks.
    • The first has a work resource assigned and spans 5/20/2013 to 5/20/2014
    • The second task is a milestone starting/ending on 5/20/2013 with a negative fixed cost (-$1,000)
    • the third task is a milestone starting/ending on 5/20/2014 with a positive fixed cost
    • After saving baseline (all tasks) and publishing the project, the MSP_EpmTaskBaselineByDay table does not include the 5/20/2013 negative baseline value for the summary task and the detail task shows zero baseline on that day
    • After changing the task's date to 5/21/2013, rebaselining and publishing, the negative baseline shows up in the reporting database on 5/21 for the Summary Task, but the detail task still shows zero baseline