Set Different Baseline Cost for one Task RRS feed

  • Question

  • Dear All,

    How to set and select different Baseline Cost for one Task or resources.

    When I set baseline cost at baseline 1, it doesn't affect on "Earned Value" Report. 



    • Edited by Jssvish Monday, November 20, 2017 6:19 AM
    Monday, November 20, 2017 6:08 AM

Answers

  • Hi,

    In the file/options dialog box, you can select which baseline (baseline 0) is used for EV calculations. Just change the default selection and choose baseline 1. Note that it applies on the entire project, this is not at task level.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    • Marked as answer by Jssvish Tuesday, November 21, 2017 4:54 AM