Show baselines values in task update RRS feed

  • Question

  • Hello,

    In the approval section, I am able to show in the right view Actual (Actual Work) and Planned (Work). I think it will be very interesting to have baseline work as well. Is there a way to make this?

    Thank you in advance,

    Thursday, October 8, 2015 2:49 PM

Answers

  • Hi,

    unfortunately there is no possibiltiy to do there. But you can open "Preview Updates". The views there can be configured (e.g. Tasks Tracking does already include Baseline Start and Baseline Finish)

    Regards
    Barbara


    To increase the value of this forum, please mark the replies that helped to solve your issue as answer. If you find answers to questions from other forum participants to be helpful, please mark them as helpful. Your participation will help others to find an appropriate solution faster. Thanks for your support!

    Thursday, October 8, 2015 3:41 PM