Customize Task Usage in Global Template to display enterprise fields from Project RRS feed

  • Question

  • I would like to customize the global template to display the fields from the Project Information at the Task Usage view (or similar custom views), but although I can add the fields to the table "Usage", but even after that, I could add to the view, and it displays "Unavailable" enterprise field.

    But I tried to add to the Task Sheet view, it works.

    So my question is: can I add the custom fields from Project Information to the Task Usage view?


    Kevin Li

    Monday, September 29, 2014 2:34 AM

All replies

  • Hi,

    Since the task and resource usage views are assignments type views, you can only add task fields assuming they get rooled down to assignments row. Meaning that you cannot add to the usage view project field (which are available in the project information dialog box).


    Hope this helps,