  • Hi, Forum.

    I am having a big problem with what data Project (2013) exports to Excel.  I have a view for "Incomplete Tasks," which means of course that I do not see tasks that have completed.  Yet when I export Project to Excel, it exports line items for tasks that have already completed.  So I have to go through the entire spreadsheet to delete/hide these tasks.  I have ensured that all of my mapping is correct.  I never had this problem with the older version of Project. 

    Any ideas?

    Thanks!

    Josh

    Tuesday, November 8, 2016 3:49 PM

All replies

  • Josh,

    First of all, is your version of Project 2013 fully updated? It should at least be at 15.0.4867.1003 which is the September2016 update. If not, run Windows Update.

    Are you using an export map or one of the visual reports? If using an export map, did you set the "Incomplete Tasks" filter on the field mapping page of the export wizard?

    John

    Tuesday, November 8, 2016 4:02 PM