Modifying Appearance of Timesheet - Project Server 2010 RRS feed

  • Question

  •  

    We do not want to display "% Work Complete" in the left hand side of the Timesheet (My Work view).   

    I have gone into Manage Views and modified time My Work view (under timesheet) to exclude - % Work Complete (See below).    Yet it still appears in the Timesheet.  What do I need to do to make this go away across the enterprise?

    Tuesday, February 19, 2013 8:02 PM

Answers

  • Hi Randy,

    any modifications on timesheet views will only apply to timesheets, created AFTER modification of view. Please try to create a new timesheet to check if your % Complete is gone there - I think it will.

    Regards
    Barbara

    Tuesday, February 19, 2013 8:16 PM
    Moderator

All replies

  • Hi Randy,

    any modifications on timesheet views will only apply to timesheets, created AFTER modification of view. Please try to create a new timesheet to check if your % Complete is gone there - I think it will.

    Regards
    Barbara

    Tuesday, February 19, 2013 8:16 PM
    Moderator
  • Thats it!   Thank you Barb!   So this will take effect next week for the users (which is fine by me).   ~RK