none
Resource Assignment work missing? RRS feed

  • Question

  • Hi,

    Just trying to use the standard views but when i go to PWA resource assignment, there is no work showing in the graph. This previously worked. Can see the line showing availability as well as table below showing various projucts & availability. after assigning a task, saving & publishing the project neither the graph or table in the reource assignments page is showing.

    Any idea where i might be going wrong?

    thanks in advance

    Tuesday, April 24, 2012 1:10 AM

All replies

  • Hi, do you see the work value in the resource assignments view, rather than the graph view.  Also within the graph view, presumably your assignments are committed (as opposed to proposed).

    Ben Howard [MVP] blog | web

    Tuesday, April 24, 2012 5:58 AM
    Moderator
  • Thanks for you response Ben,

    I can see the work in the resource assignment view. Can you explain how to commit a assignment as opposed to proposing it?

    Thanks so much.

    Wednesday, April 25, 2012 11:57 AM
  • Sure, within build team in MSProject, there is the booking type field next to the resource.  Make sure that this is committed.

    Ben Howard [MVP] blog | web

    Wednesday, April 25, 2012 12:01 PM
    Moderator
  • Thanks Ben,

    Yes resources are already committed.

    Any other possible ideas come to mind why resources are showing in assigned but not available?

    Sunday, April 29, 2012 12:09 AM