Timesheet exceeded hour RRS feed

  • Question

  • hello every body 

    there is a problem with some time sheet in the Queue  it appears  with job State "failed  and blocking correlation "
    the error is 
    TimesheetHoursPerTSLimitExceeded
    Value=3202. Exceeded the limit for number of hours in a timesheet.

    can anyone help please :)
    Wednesday, January 9, 2013 1:37 PM

All replies

  • Hello,

    What version of project are you using? Project Server 2007 or Project Server 2010?

    Check the "maximum hours per Timesheet" setting under Server Setting >> Timesheet settings and default

    If you enter moe hours than what is set for "Maximum hours per Timesheet" then you might run into this issue

    Hope this Helps!

    Thanks,

    Kiran K.

    Wednesday, January 9, 2013 2:44 PM
  • Thank you  Kiran 
    we are using 
     Project Server 2010
    and maximum number of hours per time sheet is 56 hour weekly 
    but the problem is some of users can fill more than 56

    and this is the reason for this problem 

    Wednesday, January 9, 2013 2:57 PM
  • That is strange. Normally they should message on screen whenever they try to save / submit  more hours than what we have specified in "Maximum hours per timesheet"
    Thursday, January 10, 2013 8:41 AM
  • yes the massage is appearing when you try y to submit timesheet with more than 56 hour
    but the problem is that for some time sheet is coming with some some fractional  value by default from the system :(
    and this is the  reason the for generating this issue 

    any help plz :)
    Saturday, January 12, 2013 9:47 AM