Hi,
I have a question about how to enter the real duration and real work if they are
both different from the planned data.
Let's say I have a task A planned for 5 days, this equals 40 work hours.
Then task A was actually performed in 4 days and needed 24 work hours.
When I fill in the actual duration (4 days), MSP recalculates the actual work to 32 hours, then when I modify actual work to 24 hours , MSP recalculates the actual duration to 3 days, and so on...
So how can I enter both actual data?