  • dears ,

    i have a question in the exam :

    QUESTION 24
    You are using Project Standard 2013. Management wants to see an overview of your project that shows the
    overall start and finish dates, total duration, and the name of the project. They want to see this information in a
    simple layout that does not include task details. You need to show one line item that displays all the requested
    information in the Gantt view. What should you do?
    A. Apply the Top Level Tasks filter.
    B. On the format ribbon, check the box next to Project Summary Task.
    C. Apply the default Summary Tasks filter.
    D. On the format ribbon, check the box next to Summary Tasks.
    Correct Answer: D

    i think the correct answer is B, please advice me.

    Wednesday, March 22, 2017 8:21 AM

Answers

  • Hamzeh --

    Wow, what a dumb question.  This reminds me a lot of the real questions that are asked in a real Microsoft Project certification exam.  Yes, I would agree that B is the best answer, as the Project Summary Task (Row 0 or Task 0) displays the project name, the Duration of the project, along with its current Start date and Finish date.  Hope this helps.


    Dale A. Howard [MVP]

    Wednesday, March 22, 2017 6:03 PM
    Moderator

All replies

  • dears ,

    i have a question in the exam :

    QUESTION 24
    You are using Project Standard 2013. Management wants to see an overview of your project that shows the
    overall start and finish dates, total duration, and the name of the project. They want to see this information in a
    simple layout that does not include task details. You need to show one line item that displays all the requested
    information in the Gantt view. What should you do?
    A. Apply the Top Level Tasks filter.
    B. On the format ribbon, check the box next to Project Summary Task.
    C. Apply the default Summary Tasks filter.
    D. On the format ribbon, check the box next to Summary Tasks.
    Correct Answer: D

    i think the correct answer is B, please advice me.

    Wednesday, March 22, 2017 8:20 AM
  • Hamzeh --

    Wow, what a dumb question.  This reminds me a lot of the real questions that are asked in a real Microsoft Project certification exam.  Yes, I would agree that B is the best answer, as the Project Summary Task (Row 0 or Task 0) displays the project name, the Duration of the project, along with its current Start date and Finish date.  Hope this helps.


    Dale A. Howard [MVP]

    Wednesday, March 22, 2017 6:03 PM
    Moderator
  • Hamzeh --

    I already answered your question in the Project Standard user forum.  Please do not cross post your questions.  Hope this helps.


    Dale A. Howard [MVP]

    Wednesday, March 22, 2017 6:08 PM
    Moderator
  • thank you
    Saturday, March 25, 2017 2:11 PM