Resource Assignment Select date range not wokring RRS feed

  • Question

  • The Select Date Range control is not working properly it does not change the results shown in resource assignments under resource center in Project server 2013. Any ideas? Have I missed some configuration?

    Regards, Syed Faizan ur Rehman, CBPM®,PRINCE2®, MCTS

    Tuesday, November 4, 2014 12:49 PM

All replies

  • Hi Syed,

    It does work correctly for me in my Project Online instance. Have you installed the SP1?

    Note that the date range is only available for the timephased data and not for the Gantt chart.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Tuesday, November 4, 2014 1:12 PM
    Moderator
  • Hi Guillaume,

      Yes I do understand that it works in case of TimePhased Data the thing is when I change the date range the records are not getting update. I have two on premises instances of PS2013 and the story is the same for both, can you shed some light if this can be dealt with some configuration? as far as I understand it is OOB.


    Regards, Syed Faizan ur Rehman, CBPM®,PRINCE2®, MCTS

    Wednesday, November 5, 2014 5:08 AM
  • Indeed Syed, this is not configurable. It sounds like a bug to me. Can you check if you have the SP1 installed with the latest CU? I'd suggest to upgrade with the latest version. Then if the bug persists, I'd open a support ticket with MS.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Wednesday, November 5, 2014 12:51 PM