Project Server 2013 PWA resource view RRS feed

  • Question

  • Hi all, 

    Is there any way to see the detail information of a resource in PWA? In Project Professional 2013, we can check all the task\project the resource is assigned and all the planned work for the resource under resource usage view. However, we can not find it in PWA. Any suggestion?

    Regards,

    Anna

    Tuesday, July 15, 2014 7:32 AM

Answers

  • Hi Anna,

    From the resource center, you can select one or more resources and check for their availability. You'll have a graph will all resources assignments by time periods and projects with a grid for the details.

    http://office.microsoft.com/en-us/project-server-help/view-resource-availability-HA010059812.aspx


    Hope this helps,


    Guillaume Rouyre, MBA, MCP, MCTS |

    Tuesday, July 15, 2014 9:05 AM
    Moderator