Sub task for Porject Task list RRS feed

  • Question

  • We are used MOSS 2007 we need to create a sub task for Project Task list.

    Is there any possible to create the sub task?


    Jey

    Monday, March 18, 2013 5:26 AM

All replies

  • You cannot create subtasks in SharePoint task lists.  Once way of achieving this might be to create an additional task list and use a lookup column to link the subtask to it's parent. 

    I believe you can create tasks and subtasks in Microsoft Project, this would also give you a much better visual overview of the tasks and their predecessors, but you would have to buy this.