Is there a way to make project automatically fill out every working hour? RRS feed

  • Question

  • When I change the levelling option to an hour by hour basis and am planning low effort tasks that are only planned to take a couple of hours ms project does not always automatically fill up all 8 hours of the working day with tasks, it puts like 0.3 hours a day for a couple of days. Is there anyway to fix this?
    Thursday, August 8, 2019 12:21 PM

Answers

  • lilys15,

    The simple answer, no. Project will shift work around to alleviate resource overallocation if leveling is used, but it will not "fill in" available time. That is something you have to do manually.

    Hope this helps.

    John

    Thursday, August 8, 2019 1:43 PM