Milestone on the Gant bar of Project Center 2010 RRS feed

  • Question

  • Hi,

    I created a custom Enterprise Project field which displays the date of an important milestone in a column of the table part of the Project Center.

    Is it possible to display graphically this milestone on the task bars?

    Thanks

    Wednesday, April 13, 2011 2:04 PM

Answers

  • Hi Wlid, no, that's not possible out of the box, though I think EPK did an add-on for Project Sever 2003 which did this - not sure if they took it forward though.


    Ben Howard [MVP] blog | web
    • Marked as answer by WLID1966 Wednesday, April 13, 2011 8:20 PM
    Wednesday, April 13, 2011 8:13 PM