  • Hello, 

    I wanted to know if and how can I add the week details to the Resource timesheets. Currently, the resources are logging intime on various projects and the Timesheet view has only totals by day. We want to be able to see a week total as well. Our workweek has 40 hours and it would be easier for the resource to check if they've met that constraint with this on display as well. 

    Any help is appreciated. 

    Thank you, 

    Pooja.

    Monday, September 24, 2018 6:48 AM

Answers

  • Hi,

    This is not possible by configuration, but note that the weekly total number of hours logged is displayed in the yellow ribbon of the timesheet, and is real-time updated.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller