  • Question

  • Hello,

    I am new to MS Project. I have created a new calender for my project but project show standard one instead of mine. Can anyone guide me on that.

    Zalikah..

    Tuesday, January 10, 2017 9:55 AM

Answers

  • Zalikha,

    the easiest way to show your created calendar, when selecting non working time, change the calendar being shown...this change will resolve the issue because this change is unique per view and you need to change in usage and Gantt Chart Views..This will be done for individual resource.

    Regards,

    Enam

    • Marked as answer by Zalikha Tuesday, January 10, 2017 10:14 AM
    Tuesday, January 10, 2017 10:08 AM

All replies

  • Zalikha,

    the easiest way to show your created calendar, when selecting non working time, change the calendar being shown...this change will resolve the issue because this change is unique per view and you need to change in usage and Gantt Chart Views..This will be done for individual resource.

    Regards,

    Enam

    • Marked as answer by Zalikha Tuesday, January 10, 2017 10:14 AM
    Tuesday, January 10, 2017 10:08 AM
  • Yes Great , Now its working.

    Thanks,

    Tuesday, January 10, 2017 10:14 AM