Not able to fetch "Task Status" and "Assigned To" column through OData feed RRS feed

  • Question

  • Hi,

    In Project Online Task List, there are two columns in task list i.e :

    1."Assigned To" 

    2. "Task Status"

    But when I am fetching the data through OData feed, I am not getting the "Assigned To" and "Task Status" column. 

    Can anyone have any idea, how to get the the issue resolved?

    Thanks,

    Rahul

    Tuesday, February 27, 2018 11:50 AM

All replies

  • I guess you are refering to the sync'd sharepoint task list. The "assigned to" refers to the assigned resources (resource name) and the task status to the task progress. In the odata feed TASKS, you'll find the resource name and the percentage completed (work or duration). You have in MS Project a STATUS field (late, completed, future) but it is not accessible via odata so the %complete will be your best option for the task status, unless you create a task custom field with a formula.

    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Tuesday, February 27, 2018 12:22 PM
    Moderator
  • Hi Rahul,

    You could use the SharePoint list REST API to get that data: {ProjectSiteUrl}/_api/Web/Lists/GetByTitle('Tasks')/Items if you really neeeded to.

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com | CPS | MVP | Downloads

    Tuesday, February 27, 2018 1:22 PM