Project 2013; How to configure updates and approvals such that a 9hr a day resource can contribute a double shift. RRS feed

  • Question

  • Sometimes our designers work two shifts so their regular calendar which schedules correctly into the future with 9hrs/day sometimes they will work a double shift.

    From the updates page, these hours will be slotted 8hrs on day 0, 8hrs on day 1, 3hrs on day 2?

    Monday, June 17, 2013 3:45 PM

All replies

  • in the scheduling options I set

    hours per day 24

    hours per week 168

    days per month 30

    for the project, since every task has a resource assignment I'm hoping this will not have and consequences.

    Monday, June 17, 2013 5:05 PM