Hello,
Please advise on how does Project calculate a task's Actual Duration after actual work for resources is entered in the timephased portion of Task Usage View in such a way that some values of the actual work do not correspond
to their assignment units.
In the example below, the original 5 days task has two resources assigned to it at 50% and 100% of their capacity.
After actual work for two resources was entered into the timephased sheet, Project calculated the task's duration of 5.63 days which is perfectly understandable. But how does Project come up wth the Actual Duration of 3.67 days ?
Shouldn't it calculate the task's actual duration similarly to the way it calculates the task's duration? That is, to count the number of days the task has actual work and add the portion of the last day's according to the amount of
actual work on that day? In such a case the Actual Duration would be equal to 4 days, that is , Mon, Tue, Wed and Thu instead of 3.67 days. Where is my mistake in calculations?
Thank you,
Alex
