Predeccessor question RRS feed

  • Question

  • I am creating a project schedule in MS Projects and would like to know what is the formula I would insert into the "Predecessor" column of a task in order for the task to start one day after the previous task's start date.
    Friday, May 22, 2015 4:33 PM

All replies

  • Hi,

    use 1SS+1d.

    But you can also double click on successor task to open Task Information dialog. On tab Predecessors you can select predecessor task, type and lag without knowing the exact syntax.

    Regards
    Barbara 


    To increase the value of this forum, please mark the replies that helped to solve your issue as answer. If you find answers to questions from other forum participants to be helpful, please mark them as helpful. Your participation will help others to find an appropriate solution faster. Thanks for your support!