Assignment and Project fields RRS feed

  • Question

  • Hi,

    Can someone explain how assignment cost/work fields are different from project cost/work fields.

    According to my understanding the cost of each assignment constitutes the project cost. But there seems to be a difference in the assignment cost of a project and the project cost.

    Please help me to get this clarified.

    Thanks,

    Roshni.

    Tuesday, May 29, 2018 5:11 AM

All replies

  • Hi,

    you may have fixed cost on some tasks. They will be included in Project Costs but not in Assignment Costs. Please add this column to look for any values there.

    Barbara

    Tuesday, May 29, 2018 5:35 AM
    Moderator