Task BCWP and Assignment BCWP - Is there a difference in calculation? RRS feed

  • Question

  • Hi,

        can someone tell me if BCWP at task level is calculated differently than at assignment level? I have a task with a single resource. I had assumed the task and assignment BCWP would always be the same, but this does not appear to be the case. There are slight, but not insignificant variances. Please see attached image. Can anyone explain this? BCWP highlighted in red boxes.

    Any help greatly appreciated.


    Monday, October 23, 2017 6:50 PM