Restrict the hours to be integer in timesheet RRS feed

  • Question

  • While submitting timesheet, can I restrict that the user must input hours in integer without digits?

    Thanks.


    Kevin Li

    Monday, September 29, 2014 4:16 PM

Answers

  • Kevin --

    Nope, this is not possible using the default features in Project Server.  Users can enter time in full hour units, such as 2 hours, or in decimal units, such as 5.25 hours.  There is no way to restrict this.  Instead, you would need to establish a process or methodology to restrict it.  Teach your team members to only enter time in full hour units, and then ask your project managers to watch for anyone who disobeys the methodology.  Hope this helps.


    Dale A. Howard [MVP]

    Monday, September 29, 2014 4:35 PM
    Moderator

All replies

  • Kevin --

    Nope, this is not possible using the default features in Project Server.  Users can enter time in full hour units, such as 2 hours, or in decimal units, such as 5.25 hours.  There is no way to restrict this.  Instead, you would need to establish a process or methodology to restrict it.  Teach your team members to only enter time in full hour units, and then ask your project managers to watch for anyone who disobeys the methodology.  Hope this helps.


    Dale A. Howard [MVP]

    Monday, September 29, 2014 4:35 PM
    Moderator
  • Thanks, got it.

    Kevin Li

    Tuesday, September 30, 2014 1:55 AM