Building an IMS (Master schedule) loses individual project summary baseline data RRS feed

  • Question

  • When we build our integrated master schedule, the baseline data in the individual project summary tasks is lost.

    For the purpose of building our IMS (customer deliverable), we save each project on the server as a separate MPP file (in 2010 format).  Each project has the project summary line (line 0) displayed and it shows the baseline data (cost, work, dates, etc.).

    We build the IMS by opening a new MPP file (off server) and using the subproject function with "link to project" deselected.

    When the subprojects are imported, the line representing what would have been the original schedules project summary task has no baseline data, whereas all of the individual tasks are present and have their baseline data intact

    Is there something we are missing?

    Thanks in advance,

    Dan