Project Sites:Mapping custom filed with the Deliverable List field RRS feed

  • Question

  • Hi,

    I need to publish the Actual Work of Deliverable from Project Professional 2013 to Deliverable List on the Project Site.

    I have created column in the deliverable list.

    How can we map the Actual Work Field or any custom field to any column in deliverable list on project sites?

    Wednesday, December 10, 2014 7:11 AM

Answers

  • Hi,

    As far as I know, you cannot add by configuration the actual work field in the deleverable list of the project site or any other project field. You might code some custom code to retrieve this information.

    Keep in mind that the objective of the deliverables/dependencies feature is to get the information about schedule delay based on milestones you are dependent from. Thus the relevant information is the finish date and not the actual work, since the finish date will be updated based on the actual and remaining work.



    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    • Marked as answer by GanuInMumbai Thursday, January 8, 2015 4:48 AM
    Wednesday, December 10, 2014 12:46 PM
    Moderator