[Project 2007] import from excel : it's possible set a WorkContour for assignments? RRS feed

  • Question

  • hi to all and thank in advance for your time.

    I want import an excel file into MS Project....but into the excel I have a monthly schedule of work so I have to set the assignments with a specific WorkContour.

    Any ideas ?

    thank you.


    Daniele.b75

    Wednesday, December 11, 2013 2:35 PM

All replies

  • Hi Daniele,

    I'm not sure if I get it right, but you might use the task usage view if you can structure your Excel file correctly.

    The first step would be to import only the tasks' information (name, resources, dates, metadata...).

    Then switch to task usage view, display it by month (tab format) and copy paste the numbers from Excel to the Project timephased grid.

    Hope this helps.


    Guillaume Rouyre - MBA, MCP, MCTS

    Thursday, December 12, 2013 6:45 PM