Tasks are automatically sorted RRS feed

  • Question

  • I add tasks in a project. I link them together. The tasks are shown in the order I entered them, as I wish. Then when I close and reopen the project the task are resorted. How can I avoid this?

    Wednesday, November 14, 2012 1:42 PM

All replies

  • It sounds as though in your default view you have the sort sequence set as a date (maybe start date?). You can fix this on the View:Data tab (in Project 2010) then select Sort and by ID (or Project->Sort in 2007). Save the project. Next time you open it, the tasks should be in the sequence in which you added them to the end of the WBS.

    Graham

    Wednesday, November 14, 2012 2:43 PM