    In MS Project 2016, I'm trying to run reports on only the tasks I have selected - not milestone, not any particular grouping - just ones that I selected as high-level. There has got to be a way where either my current view tasks show up or some sort of drop down box where I can choose the 20 or so tasks out of 484 of them. 

    Thank you in advance

    Monday, May 7, 2018 3:26 PM

Answers

  • snowsux,

    It only sucks if you're not on the slopes.

    I don't know of any report that will display selected tasks unless you use some type of filter. If Project's autofilter on an appropriate field won't work, then I suggest you use a flag field (e.g. Flag1) to identify those tasks you have selected. Then simply apply the filter and go from there.

    Hope this helps.

    John