  • Scenario:

    In My Project Plan for distance tracking / measurement reasons, I am using both Work & Material Resources

    "X" (Material Resources) created having Type "Fixed Duration" and Effort Driven "Yes".

    Issue:

    While tracking via status date & re-scheduling the incomplete work daily the Durations of these Material Resources are getting increased / changed while with the understanding & the concept of Material Resourcing the Run Rate should increase rather than increasing the finsh date / duration of the Task / Activity. 

    Pl advise what could be the probable cause / issue