Possible to delete MSProject 2010 Resource Plan? RRS feed

  • Question

  • Environment:

    • Server Enterprise
    • at June 2012 CU
    • using delivered and custom resource availability reporting heavily
    • almost 30% of all active schedules have associated Resource Plans and the number will continue to increase.

    Question:  Is there a delivered application-level function for deleting MSProject 2010 Enterprise Resource Plans?

    Details:  We can remove all resources from a Resource Plan, but cannot actually remove the Resource Plan once it is created.  There is no PWA Resource Plan ribbon function for deleting.  There is no option in the Server Settings, Database Administration, Delete Enterprise Objects for deleting Resource Plans.  ProjTool.exe does not include information or functions for Resource Plans.