Proposed Booking Hours RRS feed

  • Question

  • HI,

    Are the  hours assigned to an enterprise resource with a Proposed Booking Type subtracted from that resource's availability?

    Thanks.


    Judy Washington

    Wednesday, June 26, 2013 5:19 PM

All replies

  • Yes, on resource availability page select the check box for "Include proposed bookings " to see the difference.


    Hrishi Deshpande – Senior Consultant DeltaBahn
    Blog | < | LinkedIn

    Please click Mark As Answer; if a post solves your problem or Vote As Helpful if a post has been useful to you.This can be beneficial to other community members reading the thread.

    Wednesday, June 26, 2013 9:44 PM
    Moderator
  • Hi Hrishi,

    Perhaps I did not ask my question correctly. I'm aware of the proposed booking feature in the resource center. My question really has more to do with a shared resource on two projects at the same time. For example,

    Project A has Resource 1 as a Committed booking type for 40 hours per week. Project B has Resource 1 as a Proposed booking type for 40 hours per week during the same time period as Project A. Will Resource 1 show up as overallocated in the Project A schedule? Will Resource 1 show up as overallocated on Project B schedule? Will Resource 1 tasks assignments be re-scheduled in either project schedule?

    Thanks.


    Judy Washington

    Thursday, June 27, 2013 12:18 PM