none
How i can get full task notes in PWA using CSOM RRS feed

  • Question

  • I can see my notes through my publishedtask using CSOM, like code but notes in publishedtask is a string 255 characters.

    _context.Load(publishedProjectResource, p => p.Assignments);
                    _context.ExecuteQuery();
    
                    if (publishedProjectResource != null)
                    {
                        foreach (var publishedAssignment in publishedProjectResource.Assignments)
                        {
    
                            _context.Load(publishedAssignment.Task);
                            _context.ExecuteQuery();
    
                            var publishedTask = publishedAssignment.Task;
                            if (publishedTask.Name != statusAssignment.Name) continue;
                            publishedTaskNotes = publishedTask.Notes;
                            break;
                        }
                    }

    I need see my full notes, like i see on Project Professional


    • Moved by Nan_Yu Tuesday, July 26, 2016 1:51 AM
    Monday, July 25, 2016 7:02 PM

All replies



  • Hi Flávio Moreno,

    This is the forum to discuss questions and feedback for Office 365 for Developers, scope for this forum is here . I'll move your question to the MSDN forum for Project Server General Questions and Answers :

    https://social.msdn.microsoft.com/Forums/en-US/home?forum=projectserver2010general 

    The reason why we recommend posting appropriately is you will get the most qualified pool of respondents, and other partners who read the forums regularly can either share their knowledge or learn from your interaction with us. 

    Thanks for your understanding.

    Best Regards,

    Nan Yu
    Tuesday, July 26, 2016 1:49 AM
  • thank you!
    Tuesday, July 26, 2016 10:54 AM