View team effort in Resource Graph RRS feed

  • Question

  • Hi,

    I created a project and assigned resources to the activities. I want to analyze the resources availability.

    i split the window to show at the bottom the Resource Graph. the problem is that it shows me the resources one at the time.

    I would like to have a view where I can select several resources to see together.

    thanks,

    Yuval

    Monday, March 31, 2014 5:54 AM

Answers

  • Hi Yuval,

    Please refer to MVP FAQ #38 for multiple resources graph:

    http://project.mvps.org/faqs.htm#Combined Resource Graph

    Hope this helps. 



    Guillaume Rouyre - MBA, MCP, MCTS

    • Marked as answer by Yuval.p Monday, March 31, 2014 7:18 AM
    Monday, March 31, 2014 7:08 AM
    Moderator

All replies

  • Hi Yuval,

    Please refer to MVP FAQ #38 for multiple resources graph:

    http://project.mvps.org/faqs.htm#Combined Resource Graph

    Hope this helps. 



    Guillaume Rouyre - MBA, MCP, MCTS

    • Marked as answer by Yuval.p Monday, March 31, 2014 7:18 AM
    Monday, March 31, 2014 7:08 AM
    Moderator
  • Hi Guillaume,

    Thanks a lot! this is what I was looking for.

    BTW - is there an option to do this analysis and see also the Gantt chart?

    Yuval

    Monday, March 31, 2014 7:19 AM
  • You're more than welcome Yuval.

    Unfortunately not, it won't work with the Gantt Chart.

    It has to be done with a "resource oriented" view, meaning resource sheet or resource usage.

    Cheers.


    Guillaume Rouyre - MBA, MCP, MCTS

    Monday, March 31, 2014 12:57 PM
    Moderator