  • Is there a way to schedule daily backups of the entire Sharepoint/Project Server farm?
    Thursday, October 27, 2011 3:38 PM

Answers

  • Several options are available:

    1. Daily backup schedule which backs up the server entities (From PWA -> Server Settings -> Daily Schedule Backup)

    2. Here you can find a farm backup which uses a powershell script - you can wrap it in a scheduled task with your preferences

    http://technet.microsoft.com/en-us/library/dd207307.aspx

    3. Backup jobs to the databases, which should be done along, not instead, the otehr backups 

     

    HTH


    Assaf