  • Question

  • Hi,

    why does the Gant shart shows more hours then there are inputted?

    From several tasks he seems to ad always 1 extra scale.

    Monday, March 2, 2015 3:19 PM

All replies

  • Hi Bjorn,

    Your question is quite unclear.

    • First of all, which version of Project are you using?
    • Then can you give us an example with ideally a screenshot if you can?
    • Do you mean that a task which last 5 days (be aware not to confuse work and duration) is displayed in the Gantt chart in the right part with a longer bar, ie 7 or 8 days?

    Just a few hints: check if you have non-working days like Saturdays or sundays during the task, or any calendar exceptions (for both project and resource calendars). Also display the start and finish dates with the time.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |


    Monday, March 2, 2015 3:45 PM
    Moderator
  • Open the Project in Project professional --> Add two columns --> Work --> Actual Work

    Compare the values submitted by the resources vs added into the project tasks.

    Give more information for effective troubleshooting.


    Cheers. Happy troubleshooting !!! Sriram E - MSFT Enterprise Project Management

    Tuesday, March 3, 2015 12:14 AM
    Moderator