Actual hours moved in project plan RRS feed

  • Question

  • I use Project and Project Server 2010 with resources reporting their actual hours in timesheets. I reconcile these timesheets on a monthly basis so I know that the actual hours are applied to the project plans correctly. Occasionally these hours in the project plan seem to disappear. I think that it has something to do with resources entering hours in their timesheets when they have zero remaining work or remaining work that is less than the actuals they are entering.

    Is my observation correct or is there some other reason project loses hours that have been approved and published?


    Regina

    Wednesday, May 13, 2015 7:26 PM

All replies

  • Hi Regina,

       Are you doing the approvals in the system itself or outside? If resources are doing it in the system itself after approval the actual hours do become part of the project directly. 


    Regards, Syed Faizan ur Rehman, CBPM®,PRINCE2®, MCTS

    Thursday, May 14, 2015 8:01 AM