New Custom field counting days backwards from a particular task RRS feed

  • Question

  • Hi All

    I hope someone can help

    I am attempting to create a graph with data from Project online showing project risk vs distance (in days) from product launch. I can set up custom fields to represent the risk elements but unsure how, if possible, to set up a field which represents the difference between each task's start date and the product launch task's start date.

    Thanks for your help

    Matt

    Tuesday, January 2, 2018 9:09 AM

Answers

  • Issue resolved

    For anyone having the same issue - Create an enterprise custom field to tag the "product Launch" task. Then make a new column in power BI to determine the difference between today and all tasks.

    When making the graph set maximum to 0 and minimum to a high negative number.

    Then filter tasks to only those highlighted by your enterprise custom fiel

    Hope this helps someone

    • Marked as answer by Matt22365 Friday, May 4, 2018 11:06 AM
    Wednesday, January 3, 2018 4:25 PM