I have scheduled the values to appear in days in resource usage view but it is showing in hours. I am talking about project professional 2010. RRS feed

  • Question

  • I have scheduled the values to appear in days in resource usage view but it is showing in hours. I am talking about project professional 2010.

    Monday, May 21, 2012 7:07 AM

All replies

  • From where did you configured the values to be displayed in "days"?

    Abhijeet M. Mohite --------------------------------------------------------------------------------------------------------------------------------------If you found this post helpful, please "Vote as Helpful";. If it answered your question, Plase "Mark as Answer"

    Monday, May 21, 2012 7:12 AM
  • Hello Ankit,

    As far as I have seen that  though you have set your schedule options to Work in days, project will always calculate work in hours.  A day in project is defined as 8 hours with Standard calendar.
    Please see a similar thread :
    http://social.technet.microsoft.com/Forums/en-US/projectprofessional2010general/thread/a48be67c-4003-4a3e-b802-a24f2fc482c9

    Hope this helps.


    If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82