cannot figure out how to do a simple custom report in MSP 16 RRS feed

  • Question

  • Very simple - I want a Resource Budgeted Report by month, so we can see what project each person is on each month. Mostly a single project per month type of thing.

    Columns are Work per month per project.

    Rows are Resource Name then Project Name.

    I have a Master project with all of our projects in it as Subprojects. I am thinking this is the issue.

    Any ideas, templates or other ideas? I tried to create a visual report using assignments, but it did not display anything. I thought that would be the ticket, but I think my tasks that are really projects in my master are goofing the tool up.

    Thursday, January 31, 2019 10:14 PM

All replies

  • MikethePM,

    Here's a solution that might work for you. Group the Resource Usage view of the master project. First group by assignment on the Project field and then by resource on the Name field as shown in the screen shot.

    Hope this helps.

    John

    Friday, February 1, 2019 12:27 AM