none
Accept Task Update Requests in Project Server 2007 RRS feed

  • Question

  • Hi,

    In Project Server 2007, is it possible to deny Accept Task Update access for a resource who is having Project Manager permission.

    I need to deny permission only for particular resource.

    I tried the below:

    Open Manage Users

    Select the resource

    Added three categories(My Projects, My Resources, My Tasks)

    For each category i denied permission "Accept Task Update Requests"

    Saved

    After doing the above steps the resource(PM) still receives the updates from the resources(In Approve Task updates page in PWA and when he opens the plan in ms project) and he is able to accept/approve the tasks.

    Note:1. PM is the status Manager

     2. The updates are entered through My tasks page not My Timesheet page

    Is it possible to deny the access of accept task updates for a status manager ?


    K.Gokulraj

    Thursday, July 5, 2012 11:40 AM

Answers