Add column with start date in week format (1,2,3...52) RRS feed

  • Question

  • I´m integrating several schedules into a Master one. Some of these schedules are PDF and durations are setup in weeks.

    How can I add a clumn that will display the start of a task but in weeks. For example if a tasks starts JULY 09, 2014 (7/09/20014), that days is in week 28. Can I show a column that expreses that date in terms of the week of the year that day is in.

    NOTE: My timescale is already formated to see the gant diagram in weeks (1,2,3...52)

    Thanks

    Friday, June 20, 2014 4:30 PM

All replies

  • Sorry for grammar
    Friday, June 20, 2014 4:31 PM
  • Hi Enrique,

    In the options/general menu, select "W04-4" in the date format:

    

    Then the start and finish dates will be displayed with the week number and day of the week (ie 6 for friday).

     

    You cold also create a custom field with a formula using the ProjDateConv function with the pjDate_Www_dd format option. Doing this, you'll keep the default start and finish date as is and just display week number in the calculated field.

    See reference:

    http://office.microsoft.com/en-us/project-help/project-functions-for-custom-fields-HP010080956.aspx


    Hope this helps,


    Guillaume Rouyre, MBA, MCP, MCTS |

    Friday, June 20, 2014 4:46 PM
    Moderator
  • Exact formula below:

    ProjDateConv([Start];pjDate_Www_dd)


    Hope this helps,


    Guillaume Rouyre, MBA, MCP, MCTS |

    Friday, June 20, 2014 4:50 PM
    Moderator