    let's say we have two projects A and B with a common resource pool.

    The resource x is paid 100$/ day in project A, and 50$/day in project B.

    how can I use this data using the same resource pool in the two projects?

    Thank you!


    • Edited by steeee Friday, January 9, 2015 5:10 PM
    Friday, January 9, 2015 5:07 PM

All replies

  • You can use different rate tables for a single resource.  In the Resource information form fill in the $50 rate on the rate table B.

    The default rate table used in table A, but you can quickly change rate tables in assignments in the Resource usage view.  Add the Cost rate table field to the view and copy/paste or fill down to use the other rate table.

    Friday, January 9, 2015 7:03 PM