Changing the default working and non-working days RRS feed

  • Question

  • Hi

    I am trying to make a permanent (default) change in working and non-working days. I am living in Israel and our non-working days are friday and saturday. I want to configure these as the non-working days so I won't need to do it manually via the change work time menu.

    Thanks

    Chen

    PS - I am using MSP 2013

    Thursday, February 13, 2014 4:02 PM

All replies

  • You have to edit your project calendar, then select the "working week" tab, finally click on details...

    You'll go to a dialog box to set at once the working days and hours in the week.

    Here is the article that explains how to do it :

    http://office.microsoft.com/en-us/project-help/change-working-days-for-the-project-calendar-HA102809468.aspx

    Hope this helps.


    Guillaume Rouyre - MBA, MCP, MCTS

    Thursday, February 13, 2014 4:27 PM