Project Start Date – modification after project was saved. RRS feed

  • Question

  • I created new project with  a start date 01/April/2015 and saved it. Next, I change the start date to 14/April/2015 in the setup.

    However still in statistics windows I see the start date as 01/April/2015. Additionally, every new task has start date 01/April/2015.

    Could you please advise me how can I change that?

    https://social.technet.microsoft.com/Forums/getfile/644409

    MS Project Standard 2013

    Sunday, April 12, 2015 9:09 PM

All replies

  • Project Start date is setup under Project, Project Information. Which setup are you talking about?

    make sure you have Service pack 1 installed.

    If you have set a must start date or actual progress for 1st April then Project won't move them, so start date will remain on 1st April.


    Rod Gill
    Author of the one and only Project VBA Book
    www.project-systems.co.nz

    Sunday, April 12, 2015 9:50 PM
    Moderator
  • Thank you for your prompt reply.

    1.Firstly I set up project start date as 01/04/2015 in Project, Project Information and in File, Project Information and save document.

    2. Afterwards, I modified start date into 14/04/2015 in the same places.

    However, the date in Project, Project Information - Statistics was still 01/04/2015 (please check screenshot).

    3. But finally, after several openings and closing of the document the date in Statistics is correct (hard to say what is the reason).


    • Edited by Mrcnrd Monday, April 13, 2015 8:26 PM
    Monday, April 13, 2015 8:25 PM